PGNIG - Podpisanie aneksów do umów w ramach projektu "Budowa bloku gazowo-parowego w Stalowej Wol...

PGNIG - Podpisanie aneksów do umów w ramach projektu "Budowa bloku gazowo-parowego w Stalowej Woli" (191/2012)

d1tfi5f
d1tfi5f

| | KOMISJA NADZORU FINANSOWEGO | | | | | | | | | | |
| --- | --- | --- | --- | --- | --- | --- | --- | --- | --- | --- | --- |
| | | | Raport bieżący nr | 191 | / | 2012 | | | | | |
| | Data sporządzenia: | 2012-12-28 | | | | | | | | | |
| | Skrócona nazwa emitenta | | | | | | | | | | |
| | PGNIG | | | | | | | | | | |
| | Temat | | | | | | | | | | |
| | Podpisanie aneksów do umów w ramach projektu "Budowa bloku gazowo-parowego w Stalowej Woli" | | | | | | | | | | |
| | Podstawa prawna | | | | | | | | | | |
| | Art. 56 ust. 1 pkt 2 Ustawy o ofercie - informacje bieżące i okresowe | | | | | | | | | | |
| | Treść raportu: | | | | | | | | | | |
| | Zarząd Polskiego Górnictwa Naftowego i Gazownictwa SA ("PGNiG") informuje, iż w dniu 28 grudnia 2012 r. podpisane zostały aneksy ("Aneks") do: 1) Umowy kompleksowej pomiędzy PGNiG a Elektrociepłownią Stalowa Wola SA z siedzibą w Stalowej Woli ("ECSW") na dostawy paliwa gazowego, o której Zarząd PGNiG informował w raporcie bieżącym nr 34/2011 z dnia 11 marca 2011 r. ("Umowa Gazowa"), 2) Umowy pomiędzy PGNiG, spółką zależną PGNiG ? PGNiG Energia SA z siedzibą w Warszawie, TAURON Polska Energia SA z siedzibą w Katowicach a Elektrociepłownią Stalowa Wola SA z siedzibą w Stalowej Woli ("ECSW") sprzedaży energii elektrycznej, o której Zarząd PGNiG informował w raporcie bieżącym nr 35/2011 z dnia 11 marca 2011 r. ("Umowa Sprzedaży Energii"). Zgodnie z zawartymi aneksami, przedłużony zostaje termin spełnienia następujących warunków zawieszających określonych w powyższych umowach: - dostarczenie przez ECSW do PGNiG oświadczenia potwierdzającego uzyskanie finansowania projektu "Budowa bloku gazowo-parowego w
Stalowej Woli" ? w przypadku Umowy Gazowej oraz - zawarcie umowy/umów zapewniających finansowanie budowy, rozruchu i rozpoczęcia eksploatacji bloku gazowo-parowego ? w przypadku Umowy Sprzedaży Energii. Termin spełnienia warunków uległ zmianie z 31 grudnia 2012 r. na 30 kwietnia 2013 r. Powodem zmiany zapisów umów jest konieczność zapewnienia odpowiedniego okresu dla zakończenia formalności związanych z negocjacjami i podjęciem decyzji korporacyjnych. Patrz również: 1) Umowa Gazowa - raport bieżący nr 34/2011 z dnia 11 marca 2011 r., 97/2011 z dnia 8 lipca 2011 r., 2) Umowa Sprzedaży Energii - raport bieżący nr 35/2011 z dnia 11 marca 2011 r., 40/2012 z dnia 14 marca 2012 r. | | | | | | | | | | |

RAPORT BIEŻĄCY
MESSAGE (ENGLISH VERSION)
INFORMACJE O PODMIOCIE
PODPISY OSÓB REPREZENTUJĄCYCH SPÓŁKĘ

| | MESSAGE (ENGLISH VERSION) | |
| --- | --- | --- |
| | Warsaw, December 28th 2012 Execution of annexes to agreements relating to the “Construction of a CCGT Unit in Stalowa Wola” project Current Report No.191/2012 The Management Board of Polskie Górnictwo Naftowe i Gazownictwo SA (“PGNiG”) reports that on December 28th 2012 annexes were signed (“Annexes”) to: 1) Master Agreement for Supply of Gaseous Fuel between PGNiG S.A. and Elektrociepłownia Stalowa Wola S.A. (“ECSW”), on which the PGNiG Management Board reported in Current Report No. 34/2011 of March 11th 2011 (“Gas Supply Agreement”), and 2) Agreement for Sale of Electricity between PGNiG, PGNiG's subsidiary PGNiG Energia SA of Warsaw, TAURON Polska Energia SA of Katowice and Elektrociepłownia Stalowa Wola SA of Stalowa Wola (“ECSW”), on which the PGNiG Management Board reported in Current Report No. 35/2011 of March 11th 2011 (“Electricity Sale Agreement”). The newly executed annexes extend the time limit for fulfilment of the following conditions precedent provided for in the agreements: - delivery
by ECSW to PGNiG of a representation confirming that financing for the CCGT project in Stalowa Wola has been obtained - in the case of the Gas Supply Agreement, and - execution of agreement(s) securing financing for the construction, start-up and launch of operations of the CCGT unit - in the case of the Electricity Sale Agreement. The time limit for fulfilment of the conditions has been changed from December 31st 2012 to April 30th 2013, due to the need to ensure sufficient time for the completion of formalities connected with the negotiations and corporate approvals. See also:1) Gas Supply Agreement - Current Reports No. 34/2011 of March 11th 2011, 97/2011 of July 8th 2011, 2) Electricity Sale Agreement - Current Reports No. 35/2011 of March 11th 2011, 40/2012 of March 14th 2012. | |

RAPORT BIEŻĄCY
MESSAGE (ENGLISH VERSION)
INFORMACJE O PODMIOCIE
PODPISY OSÓB REPREZENTUJĄCYCH SPÓŁKĘ

d1tfi5f

| | | POLSKIE GÓRNICTWO NAFTOWE I GAZOWNICTWO S.A. | | | | | |
| --- | --- | --- | --- | --- | --- | --- | --- |
| | | (pełna nazwa emitenta) | | | | | |
| | | PGNIG | | Paliwowy (pal) | | | |
| | | (skrócona nazwa emitenta) | | (sektor wg. klasyfikacji GPW w W-wie) | | | |
| | | 01-224 | | Warszawa | | | |
| | | (kod pocztowy)
| | (miejscowość) | | | |
| | | Marcina Kasprzaka | | 25 | | | |
| | | (ulica) | | (numer) | | | |
| | | 022 5835000 | | 022 5835856 | | | |
| | | (telefon) | | | (fax) | | |
| | | pr@pgnig.pl | | www.pgnig.pl | | | |
| | | (e-mail) | | | (www) | | |
| | | 5250008028 | | 012216736 | | | |
| | | (NIP) | | | (REGON) | | |

RAPORT BIEŻĄCY
MESSAGE (ENGLISH VERSION)
INFORMACJE O PODMIOCIE
PODPISY OSÓB REPREZENTUJĄCYCH SPÓŁKĘ

PODPISY OSÓB REPREZENTUJĄCYCH SPÓŁKĘ
Data Imię i Nazwisko Stanowisko/Funkcja Podpis
2012-12-28 Mirosław Szkałuba Wiceprezes Zarządu
2012-12-28 Sławomir Hinc Wiceprezes Zarządu

RAPORT BIEŻĄCY
MESSAGE (ENGLISH VERSION)